A slope solution that combines anchored high-tensile mesh, drapery mesh, rock bolts, shotcrete and drainage. The system is verified against the measured discontinuity geometry and anchor pull-out tests.
Systems
- High-tensile mesh (TECCO, SPIDER)Anchored stabilization.Geobrugg, imported
- Hexagonal double-twist wire meshDrapery, EN 10223-3.Made by Artusa
- Shotcrete and anchoringOwn equipment and crews.Installed by Artusa
The problem
Slope instability happens at two different scales, and confusing them leads to the wrong system. Shallow instability is the surface-parallel sliding of the soil cover or the weathered rock crust, the peeling of blocks and erosion by rain; its depth rarely exceeds a few metres. Deep instability concerns the whole mass: the slip surface passes below the anchor length and cannot be solved by covering the face with mesh. Highway cuts, railway slopes, mine benches and excavation faces can carry both at the same time.
The warning signs are read on the surface. A tension crack at the crest and bulging at the toe point to deep movement; curved tree trunks, a sagging shoulder, longitudinal cracks in the pavement and muddy water from drain holes belong to the same family. Shallow movement shows as fines collecting at the toe, rills and gullies, and crust fragments peeling off the weathered layer. Water is the trigger or the accelerator in almost every case; drainage is therefore not an add-on but part of the solution itself.
How we decide
The measurement sequence: slope geometry and height, orientation and spacing of the discontinuity sets, depth of weathering, thickness of the soil cover, an estimate of the slip surface depth, rock mass classification, groundwater level and its seasonal change, depth to sound rock. Seismic action enters as a horizontal coefficient under the applicable national code (TBDY 2018 in Türkiye).
| Observation | Criterion | Decision |
|---|---|---|
| Crust peeling at the surface, small blocks | Instability limited to the weathered crust | Drapery mesh, collection at the toe |
| Surface-parallel sliding, sound rock within reach of anchors | Slip surface within the anchor length | Anchored high-tensile mesh with pre-tensioned plates |
| Large blocks from a particular set | Unstable wedge or plane | Local rock bolts, a cable net where needed |
| Weathering face decaying in the open air | Blocks interlocked, surface protection needed | Shotcrete with mesh and weep holes |
| Tension crack and toe bulging | Deep slip surface, movement continuing | Not mesh: regrading, piled solutions, deep drainage, monitoring |
The last row is the critical one. With a deep slip surface, covering the face with mesh does not stop the movement; it only hides it.
System family
| System | When it fits | Source |
|---|---|---|
| High-tensile anchored mesh | Surface-parallel instability, pre-tensioning | Geobrugg, imported |
| Cable-reinforced panels and ring net | Reinforcement at large blocks | Geobrugg, imported, and made by Artusa |
| Hexagonal double-twist wire mesh | Drapery, erosion, gabions | Made by Artusa |
| Rock bolts and ground anchors | Tying the mass into the sound zone | Installed by Artusa |
| Shotcrete and weep holes | Decaying surface, water relief | Installed by Artusa |
| Rock scaling and vegetation removal | Before every installation | Artusa crews |
Anchored mesh kits are assessed under EAD 230025-00-0106, which defines the resistances against puncturing, shearing under the plate and surface-parallel tension. Ground anchors fall under EN 1537, hexagonal double-twist mesh under EN 10223-3, wire under EN 10218-2, coatings under EN 10244-2 and EN 10245-3, shotcrete under EN 14487-1 and EN 14487-2.
Installation
The sequence starts with making the slope safe. Scaling and vegetation removal proceed from the top down; when this step is skipped, material that moves later remains under the mesh. Then come the setting-out of anchor axes, drilling, hole cleaning, bar placement and grouting. After the grout has set, the mesh is laid, plates are fitted and pre-tension is applied by torque. Where shotcrete is needed, it is applied after the mesh and the drainage weep holes are in place.
On steep faces, access is by experienced rope-access crews. Control points: drilling length and direction, grout volume compared with the theoretical volume, plate seating, torque value, mesh overlap and clip frequency, weep hole spacing, shotcrete thickness.
Acceptance and maintenance
The backbone of acceptance is the anchor pull-out test: on selected anchors a test load derived from the design load is applied, displacement is read, and if the criterion is not met the number or length of anchors is increased. The number and method of tests are written into the contract at the start. The handover file also carries the as-built anchor plan, grouting records, the pre-tension torque list, mesh overlap measurements, shotcrete thickness and core results.
Maintenance watches for settlement under plates, corrosion at anchor heads, tears and sagging in the mesh, clogged weep holes, cracks in the shotcrete and the width of the crest crack. Where measurable movement is expected, a remote monitoring system (Turkish page) reduces the inspection frequency.
Frequently asked
- Is scaling alone enough? Scaling removes loose material but does not stop weathering from producing new blocks. A lasting solution needs mesh, bolts or a barrier.
- Who decides the anchor length? The length is calculated from the slip surface depth and the bond length required in the sound zone, and the calculation is verified by the pull-out test.
- Does the specification have to name a brand? No. When performance values and the scope of the assessment document are written, competition is preserved and bids become comparable.






System and product pages (Turkish)
- Hexagonal double-twist steel wire mesh
- Anchor and bolt pull-out testing
- DELTAX® slope netting
- QUAROX® cable net
- SPIDER® spiral rope net for slope stabilization
- TECCO® SYSTEM3 anchored slope stabilization
- Slope and rock scaling
Field record
88 projects in this family in our records, 2011–2026: Türkiye, Oman, Ghana, Iraq. Under confidentiality agreements, project and client names are not published.